Once the scheduler reviews task updates or comments from an individual resource, they can either accept the percent complete or change the number based on their assessment. If this number is finalized, the “Is Verified” field must be checked.

When an export is done to Microsoft Project, all updates made to the “Is Verified” field, which are “checked” are updated. Users can track changes in the history tab in Kahua schedule